The seven phases of a KA152, and where the money gets lost
A youth exchange isn't won on the day it's approved. It's won at two boring moments: when you decide who coordinates and when you collect the participants' data. This is the whole cycle, phase by phase.
The short answer
A KA152 has seven phases and only one of them is visible from the outside. The ones that decide whether the project holds up are the first (who coordinates) and the sixth (what participant data you have before you reimburse anyone). If those two are right, the rest is just work. If they're wrong, the final report turns into chasing twenty-five people who no longer answer.
There's an uncomfortable asymmetry in European projects: what decides whether a project holds up is not what you see. What you see is the activity week, the photos, the twenty-five young people. What decides it is a spreadsheet, a form that went out on time and a conversation someone had with the National Agency back in March.
This is written for an organisation that has already run at least one project and suspects it went well by luck. The suspicion is usually right. What follows is the full cycle of a KA152 —the youth exchange— with the two exact points where an organisation loses money without noticing.
The seven phases, on one screen
Nobody tells you about them all together, and that's why it's hard to get ahead of them. There are seven, and only the sixth is visible from the outside:
- Ideas and writing. One or two weeks of brainstorming, choosing partners and matching what you want to do with what the programme scores.
- Application. Review, attach and submit.
- Evaluation and decision. This part doesn't depend on you. It takes time, and it takes longer than you've been told.
- Contracting and funding. Signing the grant agreement and the acceptance. If nothing goes wrong, the first payment arrives within the deadline set in the grant agreement itself.
- Preparation. About three months before: dates, accommodation confirmed, call for partners and the partners looking for participants.
- Implementation. The activity itself.
- Closure and reporting. Reimbursements, final report and the last payment.
One distinction separates people who have done three projects from people who have done one: a project and an activity are not the same thing. The activity is the days the exchange lasts. The project is the whole cycle, from the moment you come up with the idea until the National Agency closes the file. And a project can include more than one activity, although hardly anyone takes advantage of that.
Look at where the real time goes. Between phase 2 and phase 4 there can be months in which you do nothing and know nothing. Planning around that silence is half the job.
The twelve-workshop method
This is the most useful design rule we've come across, and it fits in two lines. A seven-day exchange does not have seven days of content:
- One day goes on arrivals, and you fill it with getting-to-know-each-other activities.
- One day goes on closing: Youthpass, return logistics and some dissemination activity about the programme itself.
- One day is usually left free, either for a cultural visit or for working on transversal skills.
That leaves four useful days. At three activities a day, that's twelve workshops. That is a project. No more, and no less.
Knowing this changes the whole design conversation: instead of arguing about an abstract theme, you sit down to fill twelve boxes. And when the application form arrives, that schedule is already written — because the application will ask you for exactly that, day by day.
Combine two themes instead of defending one
A trick that works and isn't really a trick: instead of presenting a project on a single issue, combine two. Sustainability and sport. Sport and social inclusion. Sport and mental wellbeing. You get three things at once: more workshop ideas come out, the project stops looking like the other two hundred in the call, and it fits more than one programme priority without forcing anything.
The five roles, and why the coordinator decides everything
A KA152 rests on five functions. You don't need five people —three can do it, with some overlap— but you do need every function to have a name written next to it:
- Lead facilitation. Designs and runs the activities.
- Support facilitation. Facilitation never goes solo: two people facilitating is the real minimum.
- Logistics. Travel, accommodation, materials, local transport at the venue.
- Coordination. Talks to the National Agency, talks to the partners, manages participants and usually handles the finances too.
- Writing. Drafts the application at the start and closes the final report at the end. Both, which is why it's best if it's the same person.
Of the five, the one that decides the outcome is coordination. Not because of the hours, but because of judgement. If that person knows how to get on with the National Agency, a problem gets solved in two messages. If they don't, the pillars start falling at the same time: participants arrive badly prepared, the numbers don't add up, the team isn't aligned and fires break out everywhere.
If, when you write down the five names, the same one comes up three times, you don't have a task-sharing problem. You have a continuity risk: the day that person gets ill or leaves, the project stops.
Nobody buys a flight without your approval
This is the cheapest control there is and the one that saves the most grief. The rule is announced on day one, in capital letters and with no exceptions: anyone who buys a ticket without prior approval doesn't get reimbursed.
The procedure is simple. Each participant sends their itinerary with four details —budget, stopovers, airline and times— and waits. You accept or reject it. And that cuts off at the root three things that wreck budgets:
- The person who arrives three days early and assumes the whole trip will be paid.
- The person who takes an absurd stopover that multiplies the cost.
- The person who goes over the amount for their distance band and then asks for it to be covered.
It works best in a single group with all the participants in it, not in scattered emails. One channel, one message, everyone informed at the same time. Even so, mistakes will happen: approving someone who lands two hours before the start at an airport three hours away from the venue is a classic. The rule doesn't eliminate mistakes; it eliminates the noise so the mistakes become visible.
The same logic applies to transfers at the venue. If the place can be reached from a big station, you send everyone to the same point and give them the route. If you're in the middle of the countryside, you'll have to hire a bus and pick them up. What never works is everyone making their own way to a different place.
The mistake you pay for in the final report
This is where money really gets lost, and it's a timing mistake, not a management one.
The final report will ask you for individual data on every participant: first name, surname, date of birth, country, and quite a lot more. If you didn't collect that data beforehand, you'll have to ask twenty-five people for it who went back to their lives three weeks ago and don't answer.
And here's the sentence worth writing down somewhere:
The only leverage you have to get a participant to send you a document is that you haven't paid them yet. If you've already reimbursed them, forget it.
The fix takes an afternoon and is done before anyone arrives: a single form that every participant fills in —yours and the partners'— with the data the final report will ask for, plus allergies and dietary needs, plus a few open questions about motivation.
That form does four jobs in one go:
- It fills in the final report by copy and paste, instead of by chasing people.
- It lets you filter without going over the partner's head: they select, you have a reasoned veto.
- It lets you ask for balance in gender and in the presence of people with fewer opportunities based on criteria, not on a verbal promise.
- It tells you who's coming before they're standing in front of you: who speaks the language well, who has been on projects before, who writes five lines of motivation and who writes five paragraphs.
The same goes for invoices. Daily attendance records, signed learning agreements and every invoice saved in its folder, from day one. If one day you're asked where every euro went, the answer should be opening a folder, not reconstructing a year.
Reimbursing individuals or partner organisations
There are two ways to do it, and they are not equivalent.
Direct reimbursement to each participant. Twenty-five people means twenty-five bank transfers. And if they come from outside the European Union —the neighbouring countries this action works with— bank fees appear that nobody budgeted for.
Reimbursement to the partner organisations. Five partners means five large transfers. It's cleaner and faster, but every mistake costs more. You handle it with a document signed by each organisation stating its bank details: if the details are wrong at source, the problem is theirs; if you make a mistake copying them, it's yours. It sounds bureaucratic, and it is. It's also what lets you sleep at night if anyone asks.
And one thing hardly anyone budgets for: insurance. Third-party liability for the organisation, always, and accident insurance even if everyone is an adult. A hundred or a hundred and fifty euros in a budget of tens of thousands won't be noticed, and it stops a broken ankle on a Tuesday afternoon from becoming the project's problem.
When you actually get the last instalment
This is the part where it pays to be honest, because the gap between what the paperwork says and what actually happens is large.
The grant agreement sets a deadline for the National Agency to process your final report and pay the outstanding balance. In practice, that deadline stretches: there are cases of more than a year. Before paying, they'll write to you asking for whatever document is missing and to adjust figures.
Two practical consequences, and both are about cash flow:
- Don't count on that money to fund your next activity. If your calendar depends on getting paid for closing the previous project, you have a cash-flow problem waiting to happen.
- Keep everything. The obligation to keep the documentation runs from the last payment, not from the end of the activity. And the period isn't the same for every amount: check which one applies to you in the data sheet of your grant agreement, which is where it's written down.
On writing the application form with artificial intelligence
It deserves a line, because the video covers it and because the question comes up in every conversation. The comparison Jesús uses is a good one: an AI is a crane. You can't ask it to build the house, but it lifts a lot of weight and puts it up top. With it, a form that used to take a long week can be written in three or four afternoons.
What doesn't change is whose responsibility it is. You are the ones who sign the declaration of honour, and human review is not optional. On what the rules say about this, it pays to be precise: today there is no Erasmus+ rule governing the use of AI to write applications. It neither bans it nor authorises it. Anyone who tells you either of those things is claiming more than they know.
Questions we get asked about this
When do you get the last instalment of an Erasmus+ project?
The grant agreement sets a deadline counted from the submission of the final report, but in practice it stretches: there are cases of more than a year. It's best not to count on that money to fund your next activity.
How many people do you need to run a youth exchange?
There are five roles —lead facilitation, support facilitation, logistics, coordination and writing— and they can overlap. Three people can do it, as long as every role has a name assigned to it.
What is the twelve-workshop method?
A design rule: in a seven-day exchange, one day goes on arrivals, another on closing and another is usually free or used for a visit. That leaves four useful days, at three activities a day. Twelve workshops is the real content of a project.
How long do you have to keep the project documentation?
The period runs from the last payment, not from the end of the activity, and it isn't the same for every amount. The one that applies to you is in the data sheet of your grant agreement.
Can you reimburse partner organisations instead of each participant?
Yes, and with large groups it's usually cleaner: fewer transfers and fewer bank fees, especially with partners from outside the Union. It requires a document signed by each organisation with its bank details.
The step you can take today without us
Take the last project you ran, or the one you have in mind, and write down on a piece of paper who fills each of the five roles. If one name comes up three times, you know where the bottleneck is — and that's useful even if you don't apply for anything this year.
Get in touch
Something not covered here?
Write to us with your question. We answer it — whether we work together or not.
Email: jesus@plusers.eu · A person replies within two working days, in English, Spanish, French or Italian.
Erasmus+ and European Solidarity Corps data checked on 11 November 2026 in the Erasmus+ Programme Guide 2026 and on the European Youth Portal.